Transfer Batch Size Defined Production Planning

Transfer Batch Size Defined Production Planning (TBSDPP) ensures the correct determination of transfer batch sizes for efficient and flexible management of production processes. This feature increases flexibility in processes by optimizing the start times and sequences of operations on the production line.

  • Percentage-Based Start: Allows the next job to start when a certain percentage of the job is completed. For example, when 50% of a job is completed, subsequent operations can be initiated.
  • Time-Based Start: The next operation can be activated after the job has been performed for a certain period of time. This enables more controlled management of production time.
  • Quantity-Based Start: Allows the next job to start after a certain quantity of the job is completed. This provides flexibility in the production process, enabling more efficient use of resources.