Modern APS (Advanced
Planning and Scheduling) systems do more than simply sequence jobs; they
generate feasible production plans by modeling real physical and operational
constraints on the shop floor.
Accurately defining simultaneous operation limits for resources connected to
the same production line is critical to ensure that production plans can be
executed smoothly in real operations.
This
article examines the simultaneous operation constraint defined for 20CNC01 and
20CNC02 machines on the CNC Machining Line.
Scenario:
Line-Based Simultaneous Operation Constraint
In
production lines connected through conveyors or transfer systems, some machines
cannot operate at the same time. The reasons include:
- Unidirectional
material flow on the line
- Shared transfer
mechanisms
- Shared line
capacity
- Physical
limitations preventing simultaneous loading on the same segment
In
this scenario, 20CNC01 and 20CNC02 are connected to the same CNC Machining
Line, and due to the line structure, they cannot operate simultaneously.
If
this constraint is not defined in the system, the planning engine may
theoretically schedule both machines in the same time period. However, in
reality, the conveyor flow or line capacity would not allow this, making the
plan infeasible on the shop floor.
The
CNC Machining Line contains two machines:
- 20CNC01 – CNC
Machine 1
- 20CNC02 – CNC
Machine 2
How
Is This Constraint Defined in an APS System?
The
simultaneous operation constraint is defined at the production line level
rather than at the individual machine level.
The
implementation steps are as follows:
- First, a
production line code is defined (e.g., 0000000007).
- Then, the
parameter “maximum number of resources that can operate simultaneously” is
specified for this line.
Example:
Maximum number of simultaneously operating resources = 1
- The machines
connected to the line (20CNC01 and 20CNC02) are grouped under this
production line.
With
this structure, the system ensures that only the specified number of machines
connected to the line can operate simultaneously.
APS
System Implementation Logic
After
the constraint is defined, the scheduling engine:
- Does not schedule
machines connected to the same line simultaneously.
- Ensures that the
simultaneously operating resource limit is not exceeded.
- Maintains the
production flow by placing operations sequentially.
Example:
- 08:00 – 09:30 →
20CNC01 active
- 09:30 – 11:00 →
20CNC02 active
The system automatically enforces the rule “simultaneous capacity = 1” defined for the line.
Reflection
on the Gantt Screen
This constraint can be observed on the Gantt screen as follows:
When the Gantt chart is
examined, it can be seen that 20CNC01 and 20CNC02 do not overlap on the time
axis. While one machine is active, the other remains in a waiting state.
This situation shows that
the simultaneous operation constraint defined at the line level is correctly
enforced by the system.
Concurrent
Resource Record in the Scheduled Jobs Tab
After
the APS scheduling process is completed, the constraints applied by the system
for each operation can be viewed in detail in the “Scheduled Jobs” tab.
As shown in the screen below, Line Concurrent Resource records appear in the “Assignment Status Description” field.
These
records show the time intervals during which the line-based simultaneous
operation constraint becomes active.
Example:
- Line Concurrent
Resource: T1:03.03.2026 09:00 >>> T2:03.03.2026 09:30
- Line Concurrent
Resource: T1:04.03.2026 09:00 >>> T2:04.03.2026 13:00
Here:
- T1 →
Time when the constraint starts
- T2 →
Time when the constraint ends
These
logs indicate that the scheduling engine monitors the simultaneous capacity
limit on the line over time and prevents the defined limit from being exceeded.
Why
Is This Screen Important?
This
section demonstrates that the system manages the constraint not only
theoretically but also actively at the execution level.
- The line capacity
limit has not been violated
- Alternative
resources have not been scheduled in a conflicting manner
- The constraint
has been applied based on specific time intervals